Rt. 255 Construction for Week of August 19th

Saturday, August 17, 2013
Dubois - Work to improve route 255 near the I-80 DuBois/101 interchange is continuing. When work completes in mid-October, a smoother roadway surface and new traffic signals at the I-80 ramps will provide area drivers with more efficient travel and improved traffic flow. The week of August 19 will feature the following activity: the contractor will be working on drainage along route 255 in the three-lane area. The three lanes will be flagged but the center lane and one outside travel lane will be used for northbound and southbound traffic. No major travel delays are expected but short delays may be possible during times of high-volume traffic.  PENNDOT reminds drivers to remain alert and proceed through the work zone with caution. Normal work hours are 6 am to 6 pm each weekday.
 